Electronic Construction Collaboration System – Final Phase, SPR RB02-008, 2014

(2014) Electronic Construction Collaboration System – Final Phase, SPR RB02-008, 2014. Transportation, Department of

[img]
Preview
PDF
IADOT_InTrans_Reboredo_Electronic_Construction_Collaboration_System_Final_phase_2014.pdf

File Size:2MB
[img]
Preview
PDF
IADOT_InTrans_Reboredo_Electronic_Construction_Collaboration_System_Final_phase_2014_summary.pdf

File Size:168kB

Abstract

This phase of the research project involved two major efforts: (1) Complete the implementation of AEC-Sync (formerly known as Attolist) on the Iowa Falls Arch Bridge project and (2) develop a web-based project management system (WPMS) for projects under $10 million. For the first major effort, AEC-Sync was provided for the Iowa Department of Transportation (DOT) in a software as a service agreement, allowing the Iowa DOT to rapidly implement the solution with modest effort. During the 2010 fiscal year, the research team was able to help with the implementation process for the solution. The research team also collected feedback from the Broadway Viaduct project team members before the start of the project and implementation of the solution. For the 2011 fiscal year, the research team collected the post-project surveys from the Broadway Viaduct project members and compared them to the pre-project survey results. The result of the AEC-Sync implementation in the Broadway Viaduct project was a positive one. The project members were satisfied with the performance of AEC-Sync and how it facilitated document management and transparency. In addition, the research team distributed, collected, and analyzed the pre-project surveys for the Iowa Falls Arch Bridge project. During the 2012 fiscal year, the research team analyzed the post-project surveys for the Iowa Falls Arch Bridge project AEC-Sync implementation and found a positive outcome when compared to the pre-project surveys. The second major effort for this project involved the identification and implementation of a WPMS solution for smaller bridge and highway projects. During the 2011 fiscal year, Microsoft SharePoint was selected to be implemented on these smaller highway projects. In this year, workflows for the shop/working drawings for the smaller highway projects specified in Section 1105 of the Iowa DOT Specifications were developed. These workflows will serve as the guide for the development of the SharePoint pages. In order to implement the Microsoft SharePoint pages, the effort of an integrated team proved to be vital because it brought together the expertise required from researchers, programmers, and webpage developers to develop the SharePoint pages.

Item Type: Departmental Report
Keywords: Bridges, Construction projects, Data sharing, Highways, Implementation, Information management, Project management, Software, Websites (Information retrieval), Iowa Department of Transportation, Iowa, WPMS, web-based-electronic collaboration
Subjects: Transportation
Transportation > Bridges and tunnels
Transportation > Roads and highways
Transportation > Data and Information Technology
ID Code: 18674
Deposited By: Leighton Christiansen
Deposited On: 29 Jan 2015 21:09
Last Modified: 29 Jan 2015 21:09
URI: https://publications.iowa.gov/id/eprint/18674