Performance of Nongrouted Thin Bonded PCC Overlays, Construction Report, HR-291, August 1986

(1986) Performance of Nongrouted Thin Bonded PCC Overlays, Construction Report, HR-291, August 1986. Transportation, Department of

[img]
Preview
PDF
perfotmance_nongrouted_thin_bondeed_pcc_overlays_1986_OCR_.pdf

File Size:4MB

Abstract

The Iowa road system has approximately 13,000 miles of Portland Cement Concrete Pavements, many of which are reaching the stage where major rehabilitation is required. Age, greater than anticipated traffic, heavier loads and deterioration related to coarse aggregate in the original pavement are some of the reasons that these pavements have reached this level of distress. One method utilized to rehabilitate distressed or under designed PCC pavements is the thin bonded Portland Cement Concrete overlay. Since the introduction of thin bonded overlays on highway pavements in 1973, the concrete paving industry has made progress in reducing the construction costs of this rehabilitation technique. With the advent of the shotblast machine, surface preparation costs have decreased from over $4.00 per square yard to most recently $1.42 per square yard. Other construction costs, including placement, grouting and sawing, have also declined. With each project, knowledge and efficiency have improved.

Item Type: Departmental Report
Keywords: thin Bonded PCC Overlays, Evaluation, Grout, Overlays, Pavement maintenance, Pavement performance,
Subjects: Transportation > Pavements
Transportation
Transportation > Roads and highways
Transportation > Research
ID Code: 49042