Iowa Interstate Rest Area Stabilization Ponds;HR-207, September 1979

(1979) Iowa Interstate Rest Area Stabilization Ponds;HR-207, September 1979. Transportation, Department of

[img]
Preview
PDF
hr207.pdf

File Size:2MB

Abstract

This report is presented in two parts . P a r t I takes a new look at the design of rest area stabilization ponds after nearly 10 years' experience with some of the existing ponds and in the light of new design standards issued by Iowa DEQ. The Iowa DOT is embarking on improvements t o the ponds a t some of the r e s t areas. These improvements may include installation of drainage tile around the ponds to lower the water table below the pond bottom, sealing of the ponds with bentonite clay to reduce the infiltration to limits recently established by Iowa DEQ, and the enlargement of the ponds installation of aeration equipment t o increase the pond capacity. As the Iowa DOT embarks on this improvement program, it behooves them t o make only the improvements that are absolutely necessary to achieve waste water treatment goals. These ponds are subject to an extremely seasonal load and thus the ordinary standards used for pond design are not appropriate. Thus, Part I of the report presents a rationale for design and operation of the ponds which is deemed appropriate for t h e i r unique seasonally loaded character. Part I1 of the report looks a t the feasibility of using wind power for the aeration of the ponds, if and when aeration is deemed necessary.

Item Type: Departmental Report
Keywords: Rest Areas, Stabilization Ponds, Interstate Rest Areas, HR-207
Subjects: Transportation > Roads and highways
Transportation
ID Code: 11533
Deposited By: Margaret Barr
Deposited On: 04 Oct 2011 14:01
Last Modified: 13 Dec 2017 14:28
URI: https://publications.iowa.gov/id/eprint/11533